Adding entities (pipes and manholes)

<< Click to Display Table of Contents >>

Navigation:  Sewsan 6 Quick Start Guide > Sewsan 6 Quick Start Guide: step-by-step >

Adding entities (pipes and manholes)

We will now start with an empty model, and demonstrate how to add entities. Before drawing pipes, let's first check that the Configure snaps settings are set-up correctly. Click on the icon under the current theme display:

 

SEW_QSGuide_Snap_Settings_New

 

Ensure that Snaps On is checked at the top left, and that at least Vertex / End Point has been checked. Finally, click on the top right X icon. This will ensure that when we draw pipes later, the starting/ending of the drawing procedure snaps accurately to the existing background.

 

SEW_QSGuide_Snap_Settings2_New

 

Now, to begin drawing pipes, click on the Add Pipe toolbar icon.

 

SEW_QSGuide_AddPipeButton_New

 

This launches the Quick Draw function, with which pipes can be added to existing manholes, or created from scratch. There are three different drawing modes, as indicated below. All three modes are used in this example.

 

SEW_QSGuide_DrawModesButtons

 

The Populate from Presets dialog box is also launched when adding pipes, and provides the user with an opportunity to override the default values, as set up in Model Settings, from a pipe database. Ignore this functionality, for this example, by unchecking the uppermost checkbox (remove the check mark), as seen in the image below, to only use the values as set up in Model Settings.

 

SEW_QSGuide_AddPipeCatalogue_New

 

Hover the mouse cursor over the Quick Draw modes, and you will see that, from left to right, these are Single Mode, Connected Mode and Multi-Segment Mode.

 

SEW_QSGuide_DrawModesButtons

 

First, select the Single Mode (leftmost option), in which each left-click with the mouse represents the placement of a manhole, and after two such left-clicks, a straight pipe is created between the two manholes. Next, zoom to the H174 manhole, left-click to place the first manhole, and then left-click on the H164 manhole to place the second manhole, thereby creating a pipe. Create a second (connected) pipe by, again, left-clicking on the H164 manhole, and then left-clicking on the H121 manhole. Notice that, while you hover over H164, before you click, the structure is highlighted in blue to indicate snapping to a network item.

 

SEW_QSGuide_HighlightNode

 

Finally, right-click to stop the Add Pipe procedure.

 

In order to add the second series of pipes, click on the Add Pipe icon, and select the Connected Mode (in this mode, all subsequent left-clicks after the initial left-click will create additional manholes, with pipes connected in-between). Next, zoom to the H173 manhole, and left-click on it. Proceed by left-clicking on H172, H171 and finally on H121. Finish off by right-clicking again.

 

The model should now contain five pipes and six structures, i.e. five manhole structures and one special structure defined as an ‘End Manhole’, which denotes the final drainage point of a network (or sub-network), and is required during the analysis.

 

The next section will detail how to refine the model to match the values shown in the CAD drawing.