<< Click to Display Table of Contents >> Navigation: Sewsan 6 Tutorial > Sewsan 6 Tutorial: step-by-step > Planning analysis (time simulation design) > Performing system design checks |
Apart from all the hydraulic checks that are required for a normal Time Simulation, the Planning Analysis requires some additional inputs which need to be verified. The following properties are most important when performing a design:
Gravity pipes
•Cost functions
•Design spare capacity
•Design minimum velocity
•Exists field setting
Rising mains
•Cost functions
•Design minimum velocity
•Design maximum velocity
Pumps
•Cost functions
•Design spare capacity
•Design down size
Open the Gravity pipe table, and navigate to the Exists field. All the pipes in the model have an Exists field value of ‘True’, which means that they are existing pipes. When designing the system, two options may be assigned to existing pipes, namely a new replacement pipe option, or an additional parallel pipe option. However, pipes with an Exists field value of ‘False’ are, by definition, new pipes that need to be ‘sized’, and will not have a parallel pipe option. All gravity pipes in this model have a Design Spare Capacity of 30%, and a Design Min Velocity of 0.6 m/s. All the gravity pipes in this model use Cost Function 2, which can be confirmed by navigating to the AM Cost Function field (part of the Assets field group).
Open the Rising main table, and set the Exists field to ‘True’ (double-click to change the setting), the Design Minimum Velocity to 0.6 m/s, and the Design Maximum Velocity to 1.5 m/s, respectively. The cost function has not been set for the rising main. Navigate to the AM Cost Function field, and enter a value of 1.
Pumps also have design information. Open the Pump table, and set the Exists field to ‘True’. Also set the Design Spare Capacity to 30%. Lastly, set the Design Down Size field to ‘True’ (the pump’s duty flow will be downsized to the maximum flow into the pump structure). If there is more than one pump connected to the pump structure, then the first pump’s duty flow will be calculated, and the remaining pumps’ duty flows will be set to zero.
Finally, verify that the pump uses Cost Function 1, by navigating to the AM Cost Function field.