<< Click to Display Table of Contents >> Navigation: Sewsan 6 User Guide > Hydraulic Analysis and Design > Time Simulation > Run Design > System Design Checks |
Apart from all the hydraulic checks that are required for a normal Time Simulation, the Planning Analysis (Design) requires some additional inputs which need to be verified. The following properties are most important when performing a design:
Gravity pipes
•Cost functions
•Design spare capacity
•Design minimum velocity
•Exists field setting
Rising mains
•Cost functions
•Design minimum velocity
•Design maximum velocity
Pumps
•Cost functions
•Design spare capacity
•Design down size
The gravity pipes in the model (i.e. pipes in the the Gravity Pipe table) have an Exists field which can be set. An Exists field value of "Yes", means that they are existing pipes. When designing the system two options may be given to existing pipes, namely a new replacement pipe option or an additional parallel pipe option. However, pipes with an Exists field value of “No” are by definition new pipes that need to be “sized” and will not have a parallel pipe option. All gravity pipes in the model must have a specified Design Spare Capacity (recommended value of 30%) and a Design Minimum Velocity (recommend value of 0.6 m/s). A cost function must be assigned to the gravity pipes, which can be entered in AM Cost Function field (part of the Assets field group).
The rising mains (in the Rising Main table) have Exists fields which can be set to Yes or No (as described for gravity pipes). Rising mains must have a specified Design Minimum Velocity field (recommended value of 0,6 m/s) and a Design Maximum Velocity field (recommended value of 1,5 m/s). A cost function must be assigned to the rising mains, which can be entered in AM Cost Function field (part of the Assets field group).
Pumps (the Pump table) also have design information. Pumps have similar Exists field and Design Spare Capacity fields (as described above) which can be set to Yes/No and to a recommended value of 30% respectively. Furthermore there is a Design Down Size field which can be set. If set to “Yes”, the pump’s duty flow will be downsized to the maximum flow into the pump structure. Also note, if there is more than one pump connected to the pump structure then the first pump’s duty flow will be calculated and the the remaining pumps’ duty flows will be set to zero. Finally, a cost function must be assigned to the rising mains, which can be entered in AM Cost Function field (part of the Assets field group).